This project includes the finish out of a 360,000 sf building and a 60,000 sf addition. The scope included installing a new electrical distribution system with two 6,000A, 277/480 volt primary switchboards, one 500 KW Unit substation, one 800 KW generator, one 300 KW UPS system, 15 distribution panel boards, More »
This project was accomplished at the same time as the 5th and 6th floor vertical expansion. The CUP includes state-of-the-art chillers, boilers and heat-exchanging equipment, and two large electric rooms for normal and emergency power. Three York chillers are in operation, with room to expand to five, as well as three steam-generating More »
The GameSop Headquarters included the finish out of a 360,000 sf building and a 60,000 sf addition. The Prism team installed a new electrical distribution system with two 6,000A, 277/480 volt primary switchboards, one 500 KW Unit substation, one 800 KW generator, one 300 KW UPS system, 15 distribution panel More »